Friday Street and Yoxford Roundabout
Construction works around the Friday Street roundabout and Yoxford roundabout continue with the removal of the redundant parts of the A12 and building of the footways.
Once these are complete later this summer, the landscaping work will begin with initial planting of new hedgerows, trees and grass in the autumn.
At Yoxford, to complete the works requires a weekend closure 8pm on Friday 19 June – 0500am Monday 22 June. Both roundabouts will be completed in July 2026 with landscaping planting in the Autumn.
A12 Road Improvements
In early June, we will start the next phase of the A12 improvement works. Starting in Marlesford, a new pedestrian crossing will be built along with road junction improvements, pedestrian islands and junction improvements. These works will involve night time road closures and day time traffic management. The Sizewell C works tracker will be updated throughout the works.
Park and Ride
The Park and Rides at Wickham Market and Darsham are open with Sizewell C workers parking their cars and catching a bus to get to the Leiston sites. The road adjustments completed around the Wickham Market site and the roundabout at the park and ride in Darsham continues to progress with the required traffic management removed, easing the traffic flow. Willow Marsh Lane is due to re-open at the end of June once new road kerbing, street lighting, road markings and repairs are complete.
Two Village Bypass
The Two village Bypass at Stratford St Andrews and Farnham is now in the full construction phase. Most of the works are carried out away from the existing road network, which will reduce disruption on the road network. The new works compound that will be accessed from the A12 is now operating and the speed limits along the A12 have now returned to normal (30mph through the villages of Farnham and Stratford St Andrew, 50mph on the A12 towards or coming from Ipswich). There are required utility works around Tinker Brook Lane and A12 junction which require two-way traffic lights on the A12 from 1st June
Sizewell Link Road
From the end of May Moat Road will close at the B1122 junction which will re-open when the Sizewell Link Road opens.
The closure will also include the junction of George Road and Moat Road to construct the new road configuration of this junction and will be completed 7 August 2026.
A new access to the Sizewell Link Road construction site starts on the 26 between Yoxford level crossing and Middleton Moor. The plan is to complete this work between 26 May to 5 June and will be conducted under two way lights (mon-fri 09:30-15:30). This access will initially serve construction traffic east of the rail bridge to Fordley Road
In and Around Leiston
From 8pm Friday 29 May to 5am 1 June the B1122 (Abbey Road) will be closed from Leiston Abbey to just south of Rowley Mews, and Lover’s Lane will be closed from Abbey Road to the Leiston waste recycling centre.
From 8pm 5 June to 5am 8 June and 9pm 12 June to 5am 15 June the B1122 (Abbey Road) will be closed from Potter’s Street to Eastbridge Road, and the western end of Eastbridge Road will also be closed.
Abbey Road (B1122) Diversion: B1122, A12, A1094, and B1069
Lover’s Lane Diversion: King George’s Avenue and B1122 Abbey Road
Eastbridge Road Diversion: Church Lane and Onner’s Lane will have an advisory one-way system to aid traffic flow between Eastbridge and Theberton.
College on the Coast: Phase one of Archaeology works at the college on the coast site are now complete and the contract for the construction of the college has been awarded to McLaren. McLaren will supervise and coordinate the construction of Sizewell C’s College on the Coast and its temporary accommodation campus and amenity building.