Road Closure: Buckleswood Road, Leiston
SIZEWELL C (Nuclear Generating Station) intends to make an order closing part of Buckleswood Road for approximately 370m from approximately 430m south of its junction with Abbey Lane to approximately 200m west of its transition to Westward Ho, to facilitate rail signalling testing. Other coordinated works may also take place during this period.The diversion route will be Abbey Lane, Abbey Road (B1122) and vice versa.It is intended that the closure will be in place at all hours between Monday 30th November until Friday 11th December 2026.Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.Date: 9th November 2026 -
Road Closure: B1119, Rendham Road, Saxmundham
Sizewell C (Nuclear Generating Station) Order 2022/853 – Article 19
TEMPORARY CLOSURE OF PART OF B1119, RENDHAM ROAD, SAXMUNDHAM
SIZEWELL C (Nuclear Generating Station) intends to make an order closing part of B1119, Rendham Road, as well as the dedicated right hand turn lanes at the A12/B1119 junction. The distance of the Rendham Road closure is approximately 200m. The closure is to facilitate works associated with junction improvements including road widening on the B1119 west of the A12 and widening of the dedicated right hand turn lane on the A12 Northbound.
Other coordinated works may also take place during this period.
The diversion route will be B1119, B1120, A1120, A12 and vice versa.
It is intended that the closure will operate at all hours between 8am on Monday 11th January until 8pm on Friday 19th February 2027 but will remain in place until the works are completed.
Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.
Date: 6 November 2026
-
Road Closure: Village Green, Westleton
SIZEWELL C (Nuclear Generating Station) intends to make an order closing part of Village Green, Westleton for approximately 15m from its junction with Blythburgh Road to facilitate works associated with the Sizewell C Westleton scheme.Other coordinated works may also take place during this period.The diversion route will be Baker’s Lane, Darsham Road, B1125 and vice versa unless otherwise communicated.It is intended that the closure will be in place from Wednesday 25th November 2026 to Friday 18th December 2026.Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.Date: 4 November 2026 -
Road Closure: Moat Road, Theberton from junction with B1122 Leiston Road for 1km to Moat Farm
SIZEWELL C (Nuclear Generating Station) intends to make an order closing Moat Road, Theberton from its junction with B1122 Leiston Road approximately 1km to Moat Farm to facilitate works associated with the delivery of the Sizewell Link Road.Other coordinated works may also take place during this period.The diversion route will be B1122, Pretty Road, Hawthorn Road and vice versa unless otherwise communicated.It is intended that the closure will operate 24 hours each day from Monday 23rd November 2026 until Sunday 1st October 2028.Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.Date: 2 November 2026 -
Road Closure: B1122 Abbey Road; part of Eastbridge Road and part of Lovers Lane, Leiston
SIZEWELL C (Nuclear Generating Station) intends to make an order closing part of B1122 Abbey Road from its junction with Rowley Mews to its junction with Potters Street; Eastbridge Road from its junction with B1122 Abbey Road for approximately 400m and Lovers Lane from its junction with Abbey Road to its junction with King George’s Avenue to facilitate works associated with the completion of the Plaza Roundabout.Other coordinated works may also take place during this period.The diversion route for Abbey Road will be B1069, A1094, A12, B1122 and vice versa.The diversion route for Eastbridge Road will be Eastbridge Road, Church Road and Bakers Hill / Onner’s Lane.The diversion route for Lovers Lane will be King George’s Avenue, B1122 and vice versa.It is intended that the closure will operate at all hours between 8pm on Friday 20th November until 5am on Monday 23rd November, and at all hours between 8pm on Friday 27th November until 5am on Monday 30th November. The closure will also be in place 8pm to 5am on Monday to Friday nights between 8pm on Monday 23rd November until 5am on Saturday 5th December.Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.Date: 30 October 2026 -
Road Closure: B1122 Abbey Road – 13th to 16th November
SIZEWELL C (Nuclear Generating Station) intends to make an order closing part of B1122 Abbey Road from its junction with Rowley Mews to its junction with Potters Street; Eastbridge Road from its junction with B1122 Abbey Road for approximately 400m and Lovers Lane from its junction with Abbey Road to its junction with King George’s Avenue to facilitate works associated with the completion of the Plaza Roundabout. Other coordinated works may also take place during this period.The diversion route for Abbey Road will be B1122, B1069, A1094, A12, B1122 and vice versa.The diversion route for Eastbridge Road will be Eastbridge Road, Church Road and Bakers Hill / Onner’s Lane.The diversion route for Lovers Lane will be King George’s Avenue, B1122 and vice versa.It is intended that the closure will operate at all hours between 8pm on Friday 13th November until 5am on Monday 16th November.Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.Date: 23 October 2026 -
TEMPORARY CLOSURE OF ANNESONS CORNER AND PART OF HAWTHORN ROAD, MIDDLETON
Sizewell C (Nuclear Generating Station) Order 2022/853 – Article 19
TEMPORARY CLOSURE OF ANNESONS CORNER AND PART OF HAWTHORN ROAD, MIDDLETON1
SIZEWELL C (Nuclear Generating Station) intends to make an order closing Annesons Corner and part of Hawthorn Road from its junction with Annesons Corner for approximately 300m to facilitate works associated with the delivery of Sizewell Link Road.
Other coordinated works may also take place during this period.
The diversion route will be B1122, Aldhurst Farm Road, Abbey Lane, Harrow Lane, Hawthorn Road and vice versa unless otherwise communicated.
It is intended that the closure will operate 24 hours each day from Monday 10th August 2026 to Friday 30th April 2027, but the closure will remain in place until associated works are completed.
Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.
Date: 20 July 2026
Sizewell C Information Office,
48-50 High Street,
Leiston,
IP16 4EW
info@sizewellc.com
-
TEMPORARY CLOSURE OF PART OF PRETTY ROAD, THEBERTON

Sizewell C (Nuclear Generating Station) Order 2022/853 – Article 19
TEMPORARY CLOSURE OF PART OF PRETTY ROAD, THEBERTON
SIZEWELL C (Nuclear Generating Station) intends to make an order closing PRETTY
ROAD, THEBERTON from approximately 350m from its junction with B1122 Leiston Road to approximately 220m from its junction with Hawthorn Road to facilitate the construction of Sizewell Link Road.
Unless otherwise notified, the diversion route will be B1122, Abbey Lane, Harrow Lane, Hawthorn Road and vice versa.
It is intended that the closure will operate from 29th June 2026 to 20th August 2027 but will remain in place until the works are complete.
Enquiries should be made to Sizewell C Information Office at 48-50 High Street, Leiston, IP16 4EW between 9.30am and 5pm, Monday to Friday.
Date: 2 June 2026
Sizewell C Information Office,
48-50 High Street, Leiston, IP16 4EW
info@sizewellc.com -
Sizewell C Construction Update May 2026
Introduction
The works on Sizewell C project are progressing well and on track. From Tuesday 26 May several projects will start including:
The closure of Moat Road at the B1122 junction to enable to construction of Sizewell Link Road.
B1122 road improvements at Middleton will start (nights)
New access on the Sizewell Link Road (SLR) construction site from the B1122 (between Yoxford level crossing and Middelton Moor).
A12 at Marlesford will have UKPN working to install cables for the signalised pedestrian crossing
Saxmundham Road will be temporally closed at the level crossing for utility works Road (Leiston) until 8 June, Balfour Beatty will then move the closure to facilitate track and level crossing improvements until 19 July.
We have launched a new hybrid website of the Sizewell C Works Tracker and causeway one that can be accessed from the Works Tracker. This new feature will give the community further information on traffic management and road works across the East Suffolk network which will help plan journeys and further improve accessibility. The site will include an automated table of works related to Sizewell C which is updated in real time.
Causeway one.network – Roadworks Map & List View – Sizewell C Works Tracker
Off Site Infrastructure
Friday Street and Yoxford Roundabout
Construction works around the Friday Street roundabout and Yoxford roundabout continue with the removal of the redundant parts of the A12 and building of the footways.
Once these are complete later this summer, the landscaping work will begin with initial planting of new hedgerows, trees and grass in the autumn.
At Yoxford, to complete the works requires a weekend closure 8pm on Friday 19 June – 0500am Monday 22 June. Both roundabouts will be completed in July 2026 with landscaping planting in the Autumn.
A12 Road Improvements
In early June, we will start the next phase of the A12 improvement works. Starting in Marlesford, a new pedestrian crossing will be built along with road junction improvements, pedestrian islands and junction improvements. These works will involve night time road closures and day time traffic management. The Sizewell C works tracker will be updated throughout the works.
Park and Ride
The Park and Rides at Wickham Market and Darsham are open with Sizewell C workers parking their cars and catching a bus to get to the Leiston sites. The road adjustments completed around the Wickham Market site and the roundabout at the park and ride in Darsham continues to progress with the required traffic management removed, easing the traffic flow. Willow Marsh Lane is due to re-open at the end of June once new road kerbing, street lighting, road markings and repairs are complete.
Two Village Bypass
The Two village Bypass at Stratford St Andrews and Farnham is now in the full construction phase. Most of the works are carried out away from the existing road network, which will reduce disruption on the road network. The new works compound that will be accessed from the A12 is now operating and the speed limits along the A12 have now returned to normal (30mph through the villages of Farnham and Stratford St Andrew, 50mph on the A12 towards or coming from Ipswich). There are required utility works around Tinker Brook Lane and A12 junction which require two-way traffic lights on the A12 from 1st June
Sizewell Link Road
From the end of May Moat Road will close at the B1122 junction which will re-open when the Sizewell Link Road opens.
The closure will also include the junction of George Road and Moat Road to construct the new road configuration of this junction and will be completed 7 August 2026.
A new access to the Sizewell Link Road construction site starts on the 26 between Yoxford level crossing and Middleton Moor. The plan is to complete this work between 26 May to 5 June and will be conducted under two way lights (mon-fri 09:30-15:30). This access will initially serve construction traffic east of the rail bridge to Fordley Road
In and Around Leiston
From 8pm Friday 29 May to 5am 1 June the B1122 (Abbey Road) will be closed from Leiston Abbey to just south of Rowley Mews, and Lover’s Lane will be closed from Abbey Road to the Leiston waste recycling centre.
From 8pm 5 June to 5am 8 June and 9pm 12 June to 5am 15 June the B1122 (Abbey Road) will be closed from Potter’s Street to Eastbridge Road, and the western end of Eastbridge Road will also be closed.
Abbey Road (B1122) Diversion: B1122, A12, A1094, and B1069
Lover’s Lane Diversion: King George’s Avenue and B1122 Abbey Road
Eastbridge Road Diversion: Church Lane and Onner’s Lane will have an advisory one-way system to aid traffic flow between Eastbridge and Theberton.College on the Coast: Phase one of Archaeology works at the college on the coast site are now complete and the contract for the construction of the college has been awarded to McLaren. McLaren will supervise and coordinate the construction of Sizewell C’s College on the Coast and its temporary accommodation campus and amenity building.
Rail
East Suffolk Line: As previously advertised, from 23 May Sunday 31 May. Network Rail will close the train line from Ipswich to Lowestoft; a bus replacement service will be in operation. The closure of the line is to enable civil engineering works which include laying foundations for new and improved signalling equipment, improving and maintaining ballast and electrical wiring troughing. The closure will also enable the first phase on the level crossing upgrades at Melton and Bealings. For more information please contact Network. Sizewell C has worked with Greater Anglia (GA) Rail to ensure collaborative communications. GA have confirmed that posters have been placed in all affected stations along the East Suffolk Line, station announcements and social media as part of their check before you travel. Additionally, the blockade has been advertised on the website: Service Alterations | Greater Anglia.
As part of the blockade, Sizewell C has run engineering trains along the Leiston line as part of the upgrade to the branch line and the construction of the green rail line. As train movements increase, we will publish our train movements on a weekly basis alongside our road closure bulletin on our works tracker. You can sign up to these notifications via the works tracker at: Sizewell C Works Tracker – Track SZC Projects & Get Alerts for New Activities
The Green Rail Route rail line has now been installed. The rail crossing at Abbey Road is now complete with asphalt laid and the road reopened. Level crossing gates will be installed shortly as the first trains start to arrive.
Temporary Construction Area (TCA)
The civil works for the first concrete batching plant is now complete with installation of the plant commenced. When operational, the plants will supply more than one million m3 of concrete for the construction of Sizewell C, removing the need to use HGVs to transport concrete into the site. The batching plant is made up of four individual batching plants and are on schedule to be completed later this year, ready for the major foundations works in 2027. Alongside the batching plant the desalination water plant continues to be constructed, which will supply the water required throughout the construction works.
The steel frame for the amenity building at the campus is being cut by our contractors, William Hare at their fabrication facility in North Yorkshire. The first steel frames are due on site in June ahead of a six-week build programme. McLaren’s Construction Management and Specialist Projects division will also support Sizewell C to deliver part of the accommodation campus and amenity buildings. The buildings will play a vital role in supporting Sizewell C’s workforce during the construction of the project on the Suffolk coast.
Work continues to construct the Bridleway 19 diversion along Lovers Lane and heading north on the B1122.
Main Construction Area (MCA) including Sizewell Beach
Main Development Site and Sizewell beach: The Marine Bulk Import Facility (MBIF) offshore piling work is now complete and construction from the Canti-travel Rig is ongoing. The beach is open but subject to short closures to ensure safety and will have marshals directing any walkers or beach users.
Upcoming Community Forums
Thank you for patience during these works.
To find out more about the progress of the works the next round of community forums are as follows:
Southern Transport Forum: Wednesday 3 June 1800, Stratford St Andrew Riverside Centre.
Main Development Site Forum: Wednesday 8th July 1800, at the Leiston Town Athletic Association (LTAA)
Sizewell C Community Relations Team
Regional External Affairs and Development
Sizewell C0800 197 6102
info@sizewellc.com